How to Track Building Permits in San Diego, CA

Learn how to track building permits in San Diego, CA. Get information about the Development Services Department, permit processes, and how architects can stay organized with Permitful.

Cover Image for How to Track Building Permits in San Diego, CA

San Diego, CA permits at a glance

Phone
(619) 446-5000

Tracking building permits in San Diego, California, can be a complex process, especially for architects managing multiple projects across the city. The City of San Diego's Development Services Department handles all building permits, plan review, and inspections for residential and commercial projects, along with the discretionary permits that many coastal and larger sites need first.

Understanding San Diego's Permit Process

The Development Services Department (DSD) runs applications, plan review, and inspections through Accela Citizen Access, its online permits portal, for applications submitted since 2021. Anyone can search applications there without logging in, but an account is required to submit. Older projects are searchable in OpenDSD.

Rather than one fixed turnaround, the city publishes a weekly Permit Processing Timeline showing average days for intake, first reviews, rechecks, and issuance, alongside budget goals of 20 days per building review cycle and 5 days for Rapid Review. Eligible smaller scopes get Rapid Review at no extra cost, Express Plan Check is a paid faster track, and affordable housing projects have a 30-business-day guarantee.

Challenges for Architects in San Diego

Managing permits in San Diego presents a few challenges that are specific to the city:

  • Discretionary permits first: Coastal, Site Development, and Neighborhood Development permits add a separate review before the building permit can be issued
  • Frequent plan check comments: Most projects require at least one recheck cycle

Key permit types in San Diego

Permits commonly issued through Development Services Department. Most projects need more than one.

  • Building PermitsCompliance with land use, zoning, and construction standards for new construction, additions, and remodels, including ADUs and JADUs
  • Electrical PermitsWiring, devices, and equipment, including photovoltaic and EV charging
  • Plumbing and Gas PermitsAlterations and additions to plumbing systems
  • Mechanical PermitsHVAC and refrigeration
  • Simple PermitsNo-plan MEP permits for minor residential work, issued immediately online to licensed contractors
  • Grading PermitsChanges to topography, excavation, or fill
  • Right-of-Way PermitsConstruction and improvements in the public right-of-way
  • Demolition PermitsComplete removal of a structure
  • Fire PermitsSprinkler and alarm systems
  • Residential Rooftop Solar PV PermitsRooftop photovoltaic and battery storage on single-family homes
  • Discretionary PermitsCoastal Development, Site Development, Neighborhood Development, Conditional Use, and Planned Development permits that precede the building permit

Typical review timeline in San Diego

StageTypical duration
Building construction review, per review cycle (city goal)20 days; FY2025 average 9.5 days
Rapid Review, per review (city goal)5 days; FY2025 average 3.1 days, for eligible scopes such as additions up to 750 sq ft and tenant improvements up to 10,000 sq ft
Simple Permits (no-plan MEP)Issued immediately online for licensed contractors; about 2 business days for owner-builders
Express Plan Check (paid)Typically 40-50% faster, covering the initial submittal and up to two rechecks
Preliminary Review (paid pre-submittal)20 days from the application being deemed complete
Affordable Housing Permit Now and Complete Communities Now30 business days guaranteed
Permit issuance queue after approval1-4 days by permit type, published weekly on the Permit Processing Timeline

Figures from FY2026 adopted budget, Development Services (performance measures), Permit Processing Timeline, Express Plan Check, Preliminary Review, Simple Permits. Verified October 2026.

Tips for San Diego permits

  1. Ask for Rapid Review at submittal: Formerly over-the-counter review, it costs nothing extra and is assigned when an eligible project is submitted
  2. Watch the live timeline, not a fixed number: The department publishes weekly intake, first review, recheck, and issuance figures, so quote those to clients rather than a static estimate
  3. Use the right record system: Accela holds applications since 2021 and allows anonymous searching; older projects live in OpenDSD. Accounts are required to submit online

How Permitful helps architects in San Diego

Permit Advisor
When you create a project, Permit Advisor suggests the permits it is likely to need based on its type and location, so you start with a list to review and confirm with the agency.
Public project dashboards
Share a live dashboard so clients and consultants check permit status, milestones and progress themselves, without emailing or calling you.
Milestone tracking
Never miss a deadline. Track submission dates, plan check comments, resubmittal deadlines, approvals and inspections, and see what is due next across every project.

Tracking permits in San Diego, CA?

Permitful keeps every permit, phase and milestone for a project in one place, tells you what is due next, and gives your client a live dashboard so they stop asking for status updates.

Free for your first project. No credit card required.

San Diego building department resources

Permit tracking in other cities

All cities