How to Track Building Permits in Denver, CO

Learn how to track building permits in Denver, CO. Get information about Denver Community Planning and Development, its review paths and targets, and how architects can stay organized with Permitful.

Cover Image for How to Track Building Permits in Denver, CO

Denver, CO permits at a glance

Phone
(720) 865-2700

Tracking building permits in Denver, Colorado, means following a project through several review paths and, often, several City departments. Denver Community Planning and Development reviews and inspects building projects for compliance with the Denver Building and Fire Code and the zoning code, and the Denver Permitting Office, created in 2025, coordinates review across departments.

Understanding Denver's Permit Process

Applications, payments, and inspection scheduling run through E-permits, and the public Building Permit Status page shows where a permit stands without an account. The review path is set by project type and valuation: Main and Intermediate Commercial, Residential, the walk-through Express paths for small projects, and Quick Permits for trades with no plan review.

Denver publishes target review times for each path in business days, and a review times dashboard updated daily. Since 2025, an executive order caps City review time at 180 calendar days per development application, tracked on a public dashboard, and affordable housing has a 90-day path to approval.

Challenges for Architects in Denver

Managing permits in Denver presents a few challenges that are specific to the city:

  • Multi-department review: Projects can be reviewed by up to seven City departments, which is why the Permitting Office and the 180-day cap were introduced
  • Resubmittal standards: Incomplete resubmittals are turned away, and responses must be signed and sealed by the architect or engineer of record
  • Site Development Plans first: Larger projects cannot submit for building review until the Site Development Plan is approved through the project coordinator

Key permit types in Denver

Permits commonly issued through Denver Community Planning and Development. Most projects need more than one.

  • Main Commercial ReviewCommercial projects valued over $1.5 million, or anything that does not fit the smaller review paths
  • Intermediate Commercial ReviewCommercial projects of $1.5 million or less, such as small new buildings, additions, and changes of occupancy
  • Commercial Express (Walk-Through)Projects under $750,000 with no other agency approvals, such as retail or office tenant finishes
  • Residential and Intermediate Residential ReviewNew single-family and duplex homes, additions, remodels over 1,000 sq ft, and habitable accessory structures
  • Residential Express (Walk-Through)Interior remodels of 1,000 sq ft or less, window replacements, and ground-level decks
  • Quick PermitsTrade permits issued without plan review, such as roofing, siding, electrical, mechanical, plumbing, and boilers
  • Site Development Plan (SDP)Required for new commercial buildings, major additions, and new projects of three or more residential units
  • Accessory Dwelling UnitsA zoning permit, building permit, and sewer use and drainage permit, which can be reviewed together
  • Demolition PermitsRequired to remove a structure or 40% or more of its exterior wall area
  • Landmark Design ReviewA Certificate of Appropriateness for exterior work at landmarks or in historic districts, before building permits
  • Fire Plan ReviewDenver Fire Department review of site and water plans, building construction, and life-safety systems

Typical review timeline in Denver

StageTypical duration
Main Commercial: intake / initial / resubmittal review targets2 / 20 / 10 business days
Intermediate Commercial: intake / initial / resubmittal review targets2 / 10 / 5 business days
Residential and Intermediate Residential: intake / initial / resubmittal review targets2 / 10 / 10 business days
Commercial and Residential Express: initial / resubmittal review targets2 / 2 business days
Cap on City review time per development application180 calendar days, under Executive Order 151
Affordable housing path to approval90 calendar days, counting both City and applicant time
Certificate of Demolition Eligibility (no landmark potential)Within 10 business days of a complete application

Figures from CPD Administrative Policy 131A, review targets (effective January 24, 2025), Denver Permitting Office dashboard, 90-day review for affordable housing, Certificate of Demolition Eligibility review. Verified October 2026.

Tips for Denver permits

  1. Work with a project coordinator on large projects: Projects requiring a Site Development Plan are assigned a CPD project coordinator, and building review cannot be submitted until the coordinator approves
  2. Start an SDP with a concept submittal: Site Development Plans begin with a concept submittal and a meeting with several City agencies; building and zoning permits can otherwise be applied for together
  3. Get the Certificate of Appropriateness first: At landmarks and in historic districts, apply four weeks before the Landmark Preservation Commission meeting and before applying for permits

How Permitful helps architects in Denver

Permit Advisor
When you create a project, Permit Advisor suggests the permits it is likely to need based on its type and location, so nothing is missed at the start.
Public project dashboards
Share a live dashboard so clients and consultants check permit status, milestones and progress themselves, without emailing or calling you.
Milestone tracking
Never miss a deadline. Track submission dates, plan check comments, resubmittal deadlines, approvals and inspections, and see what is due next across every project.

Tracking permits in Denver, CO?

Permitful keeps every permit, phase and milestone for a project in one place, tells you what is due next, and gives your client a live dashboard so they stop asking for status updates.

Free for your first project. No credit card required.

Denver building department resources

  • Denver Community Planning and Developmenthttps://www.denvergov.org/Government/Agencies-Departments-Offices/Agencies-Departments-Offices-Directory/Community-Planning-and-Development/Plan-Review-Permits-and-InspectionsPhone: (720) 865-2700
  • Denver Building Permit Statushttps://www.denvergov.org/buildingpermitstatus
  • Review times dashboard (updated daily)https://www.denvergov.org/Government/Agencies-Departments-Offices/Agencies-Departments-Offices-Directory/Community-Planning-and-Development/Plan-Review-Permits-and-Inspections/Average-Plan-Review-Times
  • Denver Permitting Office 180-day dashboardhttps://www.denvergov.org/My-Property/Remodeling-and-Construction/Permit-Office/Dashboard
  • E-permits (applications and inspections)https://www.denvergov.org/Government/Agencies-Departments-Offices/Agencies-Departments-Offices-Directory/Community-Planning-and-Development/E-permits
  • Commercial permitting guidehttps://www.denvergov.org/files/assets/public/v/16/community-planning-and-development/documents/ds/other-forms-and-guides/commercial-permitting-guide.pdf
  • Zoning maphttps://www.denvergov.org/maps/map/zoning
  • Development feeshttps://www.denvergov.org/Government/Agencies-Departments-Offices/Agencies-Departments-Offices-Directory/Community-Planning-and-Development/Plan-Review-Permits-and-Inspections/Development-Fees

Permit tracking in other cities

All cities